🥞 Crepe & Waffle

Food Delivery Application - Project Plan & Gantt Chart

📅 Updated: January 5, 2026 | End Date: April 30, 2026

✅ Completed Milestones

✓ M1: Requirements Complete (Dec 15, 2025)
✓ M2: Design Approval (Dec 31, 2025)

Development Start

Jan 1, 2026

End Date

Apr 30, 2026

Duration

17 Weeks

Current Phase

Backend Dev

Team Size

12 Members

📊 Overall Project Progress

P1 ✓
P2 ✓
P3
Phase 1-2 Complete (24%) Phase 3 In Progress 76% Remaining
Week 1 Start
Jan 1, 2026
Backend Alpha (M3)
Feb 19, 2026
All Apps Beta (M5-7)
Mar 26, 2026
UAT Complete (M9)
Apr 23, 2026
🚀 GO LIVE (M10)
Apr 30, 2026
Task / Phase Week 1
Completed Phases
Phase 3: Backend (Laravel)
Phase 4: Admin (React)
Phase 5: Customer App (Flutter)
Phase 6: Driver App (Flutter)
Phase 7: Website (Next.js)
Phase 8: Testing
Phase 9: Deployment

🛠️ Technology Stack

🐘
PHP Laravel
Backend API
⚛️
React JS
Admin Dashboard
📱
Flutter
Mobile Apps
▲
Next.js
Customer Website
🗄️
MySQL
Database
🔗
ERP Integration
Maximum ERP

📍 Key Milestones

✓ DONE

M1: Requirements Complete

✅ Dec 15, 2025
SRS Document, Architecture Design
✓ DONE

M2: Design Approval

✅ Dec 31, 2025
All UI/UX Designs Approved
IN PROGRESS

M3: Backend Alpha

📅 Week 7 - Feb 19, 2026
Core APIs Functional
PENDING

M4: Admin Dashboard Beta

📅 Week 11 - Mar 19, 2026
All Admin Modules Complete
PENDING

M5-M7: All Apps Beta

📅 Week 12 - Mar 26, 2026
Customer App, Driver App, Website Complete
PENDING

M8: Integration Complete

📅 Week 15 - Apr 16, 2026
All Systems Integrated & Tested
PENDING

M9: UAT Complete

📅 Week 16 - Apr 23, 2026
Client Sign-off on Testing
PENDING

M10: Production Launch

🚀 Week 17 - Apr 30, 2026
System Live in Production